Meter Bank Installation

Meter Bank Installation

Meter Bank Installation

Residential

Redhill, London, UK

A new 28-outlet gas meter bank installation was delivered within a residential development in Redhill, connected to a 2‑inch main ECV supply. The project included welded header fabrication, barrel pipework installation, 900 metres of copper outlet runs, diamond core drilling, individual ECV installations, testing, purging, and final Gas Safe certification.

A new 28-outlet gas meter bank installation was delivered within a residential development in Redhill, connected to a 2‑inch main ECV supply. The project included welded header fabrication, barrel pipework installation, 900 metres of copper outlet runs, diamond core drilling, individual ECV installations, testing, purging, and final Gas Safe certification.

Meter Bank Installation

Meter Bank Installation

Residential

Redhill, London, UK

A new 28-outlet gas meter bank installation was delivered within a residential development in Redhill, connected to a 2‑inch main ECV supply. The project included welded header fabrication, barrel pipework installation, 900 metres of copper outlet runs, diamond core drilling, individual ECV installations, testing, purging, and final Gas Safe certification.

Project Overview

Semper Services successfully delivered a high-specification 28‑outlet meter bank installation, seamlessly integrated with a 2-inch main ECV gas supply. Leveraging advanced welded header fabrication techniques, the project ensured a robust, efficient, and fully compliant gas distribution system. Designed to serve multiple residential dwellings, the installation provides precise individual metering and enhanced control, supporting safe, reliable energy delivery while meeting all relevant regulatory standards.

Scope of Works

  • Fabrication of welded headers for 28‑way meter bank

  • Installation of meter bank & barrel pipework

  • 900m of copper outlet runs to individual dwellings

  • Diamond core drilling for service entry points

  • Individual ECV & test point installation per dwelling

  • Outlet connections to residents' appliances

  • Scaffolding towers for high-access works

  • Comprehensive tightness testing & purging

Solution / Delivery

Executed with precision engineering and coordinated phased delivery:

  • Off-site fabrication of welded headers for quality control

  • Precision diamond core drilling through structure

  • Phased copper distribution installation

  • Rigorous testing regime including leak detection

  • Coordinated commissioning with residents

Outcome

The project delivered a fully operational 28-outlet meter bank system with zero recorded leaks across the extensive network. All dwellings were successfully connected with individual ECV and test points via compliant copper distribution, achieving full Gas Safe certification and significantly enhancing the safety and reliability of the building's metering infrastructure.

Project Challenges

  • Precision alignment of 28-way meter bank

  • Diamond drilling through occupied building structure

  • Coordinating distribution across multiple dwellings

Services Provided

  • Bank Fabrication

  • Diamond Drilling

  • Copper Pipework

  • Testing & Cert

  • Working at Height